Henderson and Others v Merrett Syndicates Ltd and Others
It has been suggested that their Lordships' attempt to explain the decision on Junior Books Ltd v Veitchi Co Ltd with reference to the principles in Hedley Byrne & Co Ltd v Heller & Partners Ltd was in danger of 'locking the front door but leaving open a rear window'. the intervening years have left the rear window is partially open'.
In Henderson and Others v Merrett Syndicates Ltd and Others, the House of Lords extracted from the case of Hedley Byrne & Co Ltd v Heller & Partners Ltd a broader principle.
The facts of the Henderson case concerned claims brought by Lloyds names against underwriting agents acting either as members agents or managing agents or both, in respect of huge losses suffered by the names as a result of negligent underwriting. The claims were brought both by names who were in direct contractual relationship with the underwriters and by names with whom the agents had no contractual relationship. The court held, inter alia:
- Where a person assumed responsibility to perform professional or quasi-professional services for another who relied on those services, the relationship between the parties was itself sufficient, without more, to give rise to a duty on the part of the person providing the services to exercise reasonable skill and care in doing so.
- An assumption of responsibility by a person or quasi-professional services coupled with a concomitant reliance by the person for whom the services were rendered could give rise to a tortious duty of care irrespective of whether there was a contractual relationship between the parties.
The leading judgment was given by Lord Goff who looked to the speeches of Lord Morris and Lord Devlin in Hedley Byrne for the principle upon which that decision was founded. In so doing, Lord Goff did not feel constrained by such concepts as the 'seeking and giving of information or advice nor 'the giving of information and advice by a person who is not under contractual or fiduciary obligation.’
For Lord Goff, and indeed the rest of their Lordships in Henderson, the fundamental importance of Hedley Byrne was to establish the following principle - an assumption of responsibility coupled with reliance by the claimant, which in all the circumstances made it appropriate that a remedy in law should be available. Furthermore, the assumption of responsibility could arise from a relationship between the parties that was either specific or general to the particular transaction and extended beyond the provision of information and advice to include the performance of other services.
Claims for purely economic loss can be pursued under Hedley Byrne. Lord Goff added that once a case was identified as falling within the principle of Hedley Byrne there was no need to satisfy the 'fair just and reasonable test' (applied to negligence cases generally by the House of Lords in Caparo Industries pic v Dickman).
Constraints to the broad principle enunciated by Lord Goff can be derived from the references to 'professional' or 'quasi-professional services'. Clearly that definition would include the acts of architects, engineers, surveyors and possibly contractors or sub-contractors undertaking a design function. Quaere whether it would extend to contractors or sub-contractors carrying out construction works as distinct from design. If Junior Books Ltd v Veitchi Co Ltd is followed where the common relationship in the construction industry of employer and nominated sub-contractor was considered to be a special relationship, the 'floodgates' would appear to open particularly if you consider the contractual structure in Henderson – the primary and sub-contractual relationship between the names the members agents and the managing agent. However, Lord Goff hinted at another potential restraint: the contractual chain. After distinguishing the situation arising in Henderson as 'most unusual' he went on to state:
'... that in many cases in which a contractual chain comparable to that in the present case is constructed it may well prove to be inconsistent with an assumption of responsibility which has the effect of so to speak, short-circuiting the contractual structure so put in place by the parties. It cannot therefore be inferred from the present case that other sub-agents will be held directly liable to the agents principal in tort. Let me take the analogy of the common case of an ordinary building contract, under which main contractors contract with the building owner for the construction of the relevant building, and the main contractor sub-contracts with sub-contractors or suppliers (often nominated by the building owner) for the performance of work or the supply of materials in accordance with standards and subject to terms established in the sub-contract. I put on one side cases in which the sub-contractor causes physical damage to property of the building owner, where the claim does not depend upon an assumption of responsibility by the sub-contractor to the building owner; though the sub-contractor may be protected from liability by a contractual exemption clause authorised by the building owner. But if the sub-contracted works or materials do not in the result conform to the required standard, it will not ordinarily be open to the building owner to sue the sub-contractor or supplier direct under the Hedley Byrne principle, claiming damages from him on the basis that he has been negligent in relation to the performance of his functions. For there is generally no assumption of responsibility by the sub-contractor or supplier direct to the building owner, the parties having so structured their relationship that it is inconsistent with any such assumption of responsibility. This was the conclusion of the Court of Appeal in Simaan General Contracting Co v Pilkington Glass Ltd.'
Of Junior Books, Lord Goff accepted that this case created 'some difficulty' to the above analysis; however he left it there, feeling that it was 'unnecessary ... to reconsider that decision for the purposes of the present appeal'.
The development of the law of negligence is continued in White v Jones.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.